November Project Update 2024

Significant progress continues at BASK Bokarina, with foundations and sheet-piling works now complete and the two-level basement excavation nearing finish. The first tower crane base has been poured, Basement 2 columns and lift core walls are underway, and blinding and waterproofing works are progressing. The team aims to complete PA1 and PA2 before the holiday break, with Tower Crane 1 installation upcoming.