April Project Update 2025

The BASK Bokarina project continues to progress, highlighted by the milestone pour of the first post-tension ground-level slab. The team has also begun demobilising the basement waterproofing system, opening up key work zones. Double-height columns from ground to Level 1 are taking shape, while basement retaining wall blockwork and waterproofing are nearing completion. Next month will focus on additional ground-level slab pours and advancing the ground-floor formwork deck.